How can you display only the tasks in the critical path after it has been set up?

Prepare for the Smartsheet Project Management Certification Exam. Experience diverse questions with detailed explanations, enhancing your understanding and readiness. Success awaits with effective study guides!

Displaying only the tasks in the critical path is achieved by setting a filter to exclude non-critical tasks. When you establish a critical path in your project, it includes only those tasks that directly impact the project’s finish date. By applying a filter designed to show only critical tasks, you can effectively isolate these essential components and enhance your focus on what truly matters for timely project completion. This allows project managers and team members to ensure that attention and resources are directed where they are most needed.

Utilizing filters is a powerful feature within project management tools that enables users to customize their views based on specific criteria, and in this case, focusing solely on critical tasks helps in monitoring and managing project risks effectively.

The other options, while they may have relevance in specific contexts, do not specifically address the need to isolate critical path tasks. For instance, applying a specific project layout might change the overall presentation but does not inherently limit the display to critical tasks. Expanding rows in the task list merely reveals more details about all tasks rather than focusing on critical ones. Saving project settings as a template could be useful for future projects but doesn't assist in displaying the critical path within the current project context.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy