In a Finish-to-Start dependency, what does entering '1d' in the Lag field accomplish?

Prepare for the Smartsheet Project Management Certification Exam. Experience diverse questions with detailed explanations, enhancing your understanding and readiness. Success awaits with effective study guides!

In a Finish-to-Start dependency, entering '1d' in the Lag field specifically introduces a delay of one working day after the predecessor task completes before the dependent task can commence. This means that once the predecessor finishes, there will be an additional one-day waiting period before the subsequent task begins.

This mechanism is instrumental in project scheduling as it allows managers to account for pauses or transitions that may be necessary between tasks, ensuring that team members can adequately prepare for the next phase of work or that other conditions are met before initiation. The use of lag time is particularly useful in environments where tasks are interdependent, and timing is critical for resource allocation and workflow efficiency.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy