What are the three Baseline columns used in project management?

Prepare for the Smartsheet Project Management Certification Exam. Experience diverse questions with detailed explanations, enhancing your understanding and readiness. Success awaits with effective study guides!

In project management, baselines are essential as they represent the original plan for the project and serve as a basis for measuring performance and progress. The three Baseline columns that are standard in project management practices are "Baseline start," "Baseline finish," and "Variance."

  • Baseline start indicates the planned start date for a project or task according to the original project schedule. It establishes a reference point for tracking when the project was intended to begin.
  • Baseline finish refers to the planned completion date for a project or task. This provides a targeted timeline against which actual performance is measured.

  • Variance measures the difference between the baseline and the actual performance indicators, such as the actual start and finish dates. This helps project managers understand how well the project is performing relative to its original plan.

Having these three columns allows project teams to monitor deviations from the original schedule, assess the impact of any changes, and ensure that corrective measures can be taken to align actual performance with project goals. This is crucial in maintaining control over project timelines and ensuring successful delivery. Other options do not align with the standard terminologies used in project management for baseline measurement.