Which feature can help visualize dependencies between tasks in Smartsheet?

Prepare for the Smartsheet Project Management Certification Exam. Experience diverse questions with detailed explanations, enhancing your understanding and readiness. Success awaits with effective study guides!

The feature that helps visualize dependencies between tasks in Smartsheet is the predecessor columns in the Gantt Chart. This feature allows users to establish relationships between different tasks by indicating which tasks must be completed before others can begin. By setting up these dependencies, you can effectively create a visual representation of the project schedule, clearly illustrating how tasks are interconnected.

When viewing a Gantt Chart with these relationships established, users can see not only the overall timeline but also how delays in one task might impact subsequent tasks. This helps project managers make informed decisions regarding scheduling and resource allocation, ensuring smoother project execution.

While other options may serve useful functions within Smartsheet, they do not specifically focus on visualizing dependencies between tasks. Activity logs track changes and updates, milestones represent key markers in the project timeline, and work breakdown structures help in organizing tasks hierarchically, but none of them provides the same visual clarity regarding task dependencies as the predecessor columns in the Gantt Chart.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy